Charles Harwood Memoral Complex- Master Planning & Design | 2021 | Q2 2023 | Design | FEMA Public Assistance Program | St. Croix | $8,410,251.00 | Design | Flad & Associates, Inc | |
Charles Harwood Modular Temporary Parking Lot | 2021 | Q2 2022 | Temporary Construction | FEMA Public Assistance Program | St. Croix | $1,306,444.96 | Closeout | CMA International | J. Benton Construction, LLC |
VI Board of Nurse Licensure Building Replacement Project | 2022 | Q4 2024 | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $385,000.00 | Design | Springline Architects | |
John S. Moorehead Complex: Communicable Disease Clinic Generator and Administration Buildings | 2022 | Q4 2025 | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $- | Procurement | Pending | |
John S. Moorehead Complex: Environmental Health, Woman's Resources, Chemical Storage, Maintenance, Payroll, Director, Storage, Guard Shack Buildings and Grounds | 2022 | Q4 2025 | Permanent Construction | FEMA Public Assistance Program | St. Thomas | | Procurement | Pending | |
Old Mental Health Building Demolition (Parking Lot ) & STT Clinic Interior Build Out | 2021 | Q4 2025 | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $71,500.00 | Design | Springline Architects | |
John S. Moorehead Complex: HIT Building and Vital Statistics Buildings Project | 2022 | Q4 2025 | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $- | Procurement | Pending | |
Charles Harwood Memorial Complex Replacement Project | 2022 | Q3 2026 | Permanent Construction | FEMA Public Assistance Program | St. Croix | $1,766,627.42 | Contract Development | Flad & Associates, Inc | Lemartec (Abatement & Demolition) |
Eldra Schulterbrandt Long Term Mental Health Building and Annex | Not Available | Not Available | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $- | Project Development | | |
Morris DeCastro Clinic Project | Not Available | Not Available | Permanent Construction | FEMA Public Assistance Program | St. John | $- | Project Development | | |
Kund Hansen Tower Project | Not Available | Not Available | Permanent Construction | FEMA Public Assistance Program | St. Thomas | $- | Project Development | | |
Relocation of Public Helath Laboratory, Ancillary Support Facilities, and Critical Support Storage Containers | Not Available | Not Available | Temporary Construction | FEMA Public Assistance Program | St. Croix | $- | Project Development | | |
WIC Knud Hansen Reubuild Project | 2019 | Q3 2023 | Permanent Construction | US Department of Agriculture Food and Nutition Services Program | St. Thomas | $3,573,935.00 | Construction | Springline Architects | J. Benton Construction, LLC |
WIC Frederiksted Renovation Project- Phase I | 2019 | Q3 2023 | Permanent Construction | US Department of Agriculture Food and Nutition Services Program | St. Croix | $714,784.60 | Contract Development | Springline Architects | Heights Construction |
Eldra Schulterbrandt Behavioral Health Facility Generator and EnclosureBuilding | 2021 | Q4 2023 | Permanent Construction | FEMA Hazard Mitigation Program | St. Thomas | $- | Design | Department of Public Works | |
Anna's Hope Behavioral Health Facility (Design) | 2019 | Q4 2023 | Design | Local Funds | St. Croix | | Procurement | Pending | |
WIC Frederiksted Wind Retrofitting Project- Phase II | 2020 | Q1 2024 | Permanent Construction | FEMA Hazard Mitigation Program | St. Croix | | Not Started | | |